What Causes Cost Overrun in Transport Infrastructure Projects?"

Bent Flyvbjerg, Mette K. Skamris Holm, Søren L. Buhl

Original paper · DOI Submitted to arXiv on 16 Apr. 2013 Transport Reviews, vol. 24, no. 1, January 2004, 3-18 License: NONEXCLUSIVE-DISTRIB 1.0

The essentials

  • Study by Bent Flyvbjerg, Mette K. Skamris Holm, and Søren L. Buhl on cost overrun in transport infrastructure projects
  • Analysis of 258 rail, bridge, tunnel, and road projects totaling US$90 billion
  • Factors contributing to cost escalation: project implementation phase length, project size, type of project ownership
  • Significant correlation between cost escalation and duration of implementation phase
  • Importance of proactive decision-making and efficient planning to mitigate risks
  • Trend towards larger projects over time; bridges and tunnels experience higher percentage cost escalations with increased project size
  • Need for careful consideration when undertaking large-scale infrastructure projects
  • Influence of project ownership on cost escalation: accountability mechanisms are critical determinants rather than public or private ownership
  • Significance of addressing potential delays and escalating costs through proactive measures at all stages of transport infrastructure projects

Key points written by AI: they may contain errors, check them against the paper.

AI-generated keywords: Cost Overrun Transport Infrastructure Projects Implementation Phase Project Size Project Ownership

Read further

  • Comprehensive Summary
  • Layman's Summary
  • Blog article
  • Original abstract
In their study titled "What Causes Cost Overrun in Transport Infrastructure Projects? ", authors Bent Flyvbjerg, Mette K. Skamris Holm, and Søren L. Buhl present findings from a comprehensive analysis of 258 rail, bridge, tunnel, and road projects totaling US$90 billion. The research focuses on identifying factors contributing to cost escalation in these infrastructure projects by examining the impact of project implementation phase length, project size, and type of project ownership. The study reveals a significant correlation between cost escalation and the duration of the implementation phase. Delays and extended timelines during this phase pose substantial risks for cost overruns. This highlights the importance of proactive decision-making and efficient planning to mitigate these risks. Furthermore, the research shows a trend towards larger projects over time with bridges and tunnels experiencing higher percentage cost escalations as project size increases. This emphasizes the need for careful consideration when undertaking large-scale infrastructure projects. The study also challenges common assumptions about the influence of project ownership on cost escalation. While it is often believed that private ownership may be more effective in controlling costs compared to public ownership, the findings indicate that accountability mechanisms play a more critical role in determining cost outcomes. Overall, this study underscores the significance of addressing potential delays and escalating costs through proactive measures during all stages of transport infrastructure projects. These findings have significant policy implications for stakeholders involved in infrastructure development and management.

Was this synthesis useful?

Score: 0

Why do we need votes?

Votes are used to determine whether we need to re-run our summarizing tools. If the count reaches -10, our tools can be restarted.

Ask questions about this paper to our AI assistant

You can also chat with multiple papers at once here.

⚠The license of the paper does not allow us to build upon its content and the AI assistant only knows about the paper metadata rather than the full article.

Figures and plots

Ask about a figure by number or use its question button to request visual analysis. Up to two figures and four image panels per question. Values read from plots are approximate; check the original data.

AI assistant instructions?

Tools for this paper

Explain it differently 3 free rewrites left today
Save to a collection Group papers in collections to compare them, chat with them and export them. Create a free account Log in

Advanced tools Premium

For researchers who follow a field closely: citation alerts, journal-club slides, version comparison and Zotero export. Discover Premium

Zotero
Citation alerts
Journal club Slides to present it
For journalists Press kit and hype check

Similar papers summarized with our AI tools

Navigate through even more similar papers through a

tree representation

The previous summary was created more than a year ago and can be re-run (if necessary) by clicking on the Run button below.

⚠The license of this specific paper does not allow us to build upon its content and the summarizing tools will be run using the paper metadata rather than the full article. However, it still does a good job, and you can also try our tools on papers with more open licenses.

Disclaimer: The AI-based summarization tool and virtual assistant provided on this website may not always provide accurate and complete summaries or responses. We encourage you to carefully review and evaluate the generated content to ensure its quality and relevance to your needs.